Document Overview

This contribution proposes a work plan for the Study Item "Beyond 2D Video Phase 2" (FS_Beyond2D_Ph2), which focuses on dynamic mesh technologies for mobile applications. The document has been revised from an earlier version (S4-260139) with updated timelines and refined objectives.

Study Item Objectives

The study encompasses five main technical areas:

1. Dynamic Mesh Content Generation for Prosumer Use Cases

  • Focus on offline production scenarios (e.g., social media services)
  • Limited camera setup (less than 5 cameras)
  • Offline production and compression workflows

2. Dynamic Mesh for Real-Time Services

  • Live applications (e.g., concerts, sports training on social media)
  • Real-time compression requirements
  • Note: Avatar-mesh-based real-time communication is explicitly out of scope

3. Evaluation of Dynamic Mesh Formats

  • Assessment of existing and emerging compression technologies (e.g., MPEG V-DMC with HEVC as underlying 2D codec)
  • Objective and subjective testing methodology similar to TR 26.956 approach for V-PCC
  • Use V-PCC as baseline for comparison
  • Reuse of existing performance results from MPEG or other SDOs where applicable
  • Option for independent 3GPP evaluation if suitable results unavailable

4. Implementation Aspects Study

  • Number of required video decoders
  • Pixel rate limitations

5. Comparative Analysis and AI Quality Assessment

  • Compare dynamic mesh with other formats
  • Derive recommendations for format selection under different conditions
  • New: Develop framework for assessing quality of AI-generated dynamic meshes without requiring reference or original model

Proposed Timeline

SA4#134 (November 2025, Dallas)

  • Target: Agreement/Endorsement of Study Item
  • Completion: 0%

SA#110 (December 2025, Baltimore)

  • Target: Approval of Study Item
  • Completion: 0%

SA4#135 (February 2026, India)

  • Activities: Initiate work on Objectives 1a-c, 2, and 3a-b
  • Priority documents: Time Plan, TR Skeleton and Scope, Draft Use Cases/Scenarios
  • Target Completion: 20%

SA4#135-bis-e (April 2026)

  • Activities:
  • Progress work on Objectives 1a-c, 2, 3a-b
  • Initial work on Objective 1d (evaluation) and 3c-d (implementation aspects and comparison)
  • Target Completion: 45%

SA4#136 (May 2026, Montreal)

  • Activities:
  • Progress Objectives 1d and 3c-d
  • Initiate potential normative work and conclusions
  • Communication with other 3GPP WGs and external organizations
  • Identify remaining open issues
  • Agree on TR 26.xxx for SA information
  • Target Completion: 75%

SA#112 (June 2026, Singapore)

  • Activities: Present TR 26.xxx to SA for information
  • Target Completion: 75%

SA4#137-e (August 2026, online)

  • Activities:
  • Complete Objectives 1d and 3c-d
  • Complete identification of potential normative work
  • Complete all remaining open issues
  • Agree on TR 26.xxx for SA approval
  • Present TR 26.xxx to SA for information
  • Target Completion: 100%

SA4#138 (November 2026, Calgary)

  • Activities:
  • Complete evaluation work
  • Complete implementation aspects study
  • Complete comparative analysis
  • Finalize conclusions and normative work identification
  • Agree on TR 26.xxx for SA approval

SA#114 (December 2026, Boston)

  • Activities: Send TR 26.xxx to SA for Approval

Key Changes from Previous Version

  • Timeline extended and adjusted (meetings shifted from 2025-2026 to 2025-2026 with different completion targets)
  • Refined objective descriptions with clearer sub-categorization (Objectives 1a-d, 2, 3a-d)
  • Added explicit framework development for AI-generated dynamic mesh quality assessment
  • Clarified priority document types for initial meetings
  • Updated meeting locations and dates
Document Information
Source:
China Mobile Com. Corporation
Type:
Work Plan
For:
Agreement
Original Document:
View on 3GPP
Title: Proposed Timeplan for FS_DMesh_MED
Agenda item: 18.1
Agenda item description: New Work Items and Study Items for Rel-20 5G-Advanced
Doc type: Work Plan
For action: Agreement
Contact: Jiayi Xu
Uploaded: 2026-02-03T13:15:08.430000
Contact ID: 89460
TDoc Status: noted
Reservation date: 03/02/2026 12:03:32
Agenda item sort order: 89