# Summary of 3GPP Technical Document S4-260074

## Document Overview

This document presents revision 0.4 of the Work Plan for the Study Item "Study on Media Energy Consumption Exposure and Evaluation Framework phase 2" (FS_Energy_ph2_MED). The study was approved at SA4#132 (S4-251182) and SA#108 (SP-250636).

## Background and Motivation

The study addresses incomplete work from TR 26.942 v2.0.0 due to dependencies on other 3GPP groups. The phase 2 study aims to:
- Incorporate new information from completed 3GPP work
- Address key issues identified but not resolved in phase 1
- Propose new potential solutions

## Study Objectives

### 1. Release 20 Requirements from TS 22.261

The study addresses new Rel-20 requirements in the media delivery context:

**Clause 6.15a.2 - Energy-related information as service criterion:**
- Media delivery performance degradation (QoS adjustment, bit rate modification, deferring Background Data Transfers) in response to network energy supply mix changes or energy rationing
- Per-UE energy saving actions based on subscription policies, including blocking media delivery
- Mechanisms to assist Media Application Providers in identifying UEs for performance degradation and energy saving actions
- All subject to operator policy, regulatory requirements, and user consent

**Clause 6.15a.5 - Energy-related information exposure:**
- Exposure to UEs and authorized third parties over specific time periods
- Network energy consumption and equivalent CO2e emissions for overall media delivery service and individual application data flows
- Subject to operator policy, regulatory requirements, and user consent

### 2. Update Existing Solutions

Update or develop existing potential solutions incorporating new elements from TS 23.501, TS 23.502, and TS 23.503, including:
- Energy Information Function (EIF)
- Efficient energy use mechanisms
- Energy saving items

### 3. New Potential Solutions

Propose solutions for key issues on:
- Energy-related monitoring and measurement during media consumption
- Evaluation frameworks without identified normative work

### 4. New Key Issues from Phase 1

**a. Energy-related configuration by Media Application Service Provider:**
- How ASPs can configure energy-related information collection and exposure

**b. AS Energy Management:**
- How 5GMS AS (and RTC System equivalent functions) react to energy-related information from the network via Energy Information AF instantiated in 5GMS AF and/or Energy Information Collector

**c. Client Energy Management:**
- How 5GMS Client (and RTC System equivalent functions) react to network-shared energy-related information
- Leverage existing QoS optimization mechanisms in RTC/5GMS for energy efficiency optimization

## Timeline Adjustments

**Original Plan:** Completion by March 2026 (SA#111)

**Revised Plan:** Completion postponed to June 2026 (SA#112)

**Rationale:**
- Original timeline too ambitious for two SA4 meetings
- Additional two SA4 meetings provided
- Addresses Rel-20 SA1 requirements while respecting Rel-20 Stage 2 freeze
- Stage 2 addressed in single meeting, Stage 3 in two meetings

**Key Decisions to Enable Revised Timeline:**
- No new candidate solutions accepted after SA4#135
- Consensus on Stage 2 draft WID during SA4#135-bis e-meeting
- Begin Stage 2 Technical Specification work before WID approval at SA#112 by submitting discussion papers to SA4#135-bis and/or SA4#136
- Early drafts of TS 26.nnn V0.0.1/V0.0.2 based on agreed baseline of Solution 5

## Detailed Work Plan

### SA4#132 (May 2025, Fukuoka, JP)
- Agreed New Study Item FS_Energy_ph2_MED (S4-251182)

### SA#108 (June 2025, Prague, CZ)
- Approved New Study Item FS_Energy_ph2_MED (SP-250636)

### SA4#133-e (July 2025, online)
- No actions

### SA4 MBS SWG AHG Meeting (Sep 2025, Paris, FR)
- Address Rel-20 TS 22.261 requirements in media context (existing/new key issues)
- Describe new key issues: ASP configuration, AS energy management, client energy management

### SA#109 (Sep 2025, China)
- No actions

### SA4 MBS SWG AHG Telco (Oct 2025)
- Progress work on key issues
- Update/develop potential solutions on existing key issues
- Initiate work on new potential solutions for new key issues

### SA4#134 (Nov 2025, Dallas, US)
- Finalize work on key issues
- Update/develop potential solutions on existing key issues
- Progress work on new potential solutions
- Communicate with other 3GPP WGs and external organizations

### SA#110 (Dec 2025, Baltimore, US)
- No actions

### SA4 MBS SWG AHG Telcos (Dec 2025, Jan 2026)
- Update/develop potential solutions on existing key issues
- Progress work on new potential solutions

### SA4#135 (Feb 2026, Goa, IN)
- Finalize work on potential solutions
- Describe/improve potential normative work
- Agree CRs to TR 26.942
- Communicate with other 3GPP WGs and external organizations

### SA#111 (Mar 2026, Fukuoka, JP)
- ~~Approve CRs to TR 26.942~~ (changed to "No actions")

### SA4 MBS SWG AHG Telcos (Mar 2026)
- Finalize work on potential solutions submitted before SA4#135
- Progress on phase 2 modifications in conclusions
- Progress on/describe or improve potential normative work and further study

### SA4#135-bis e-meeting (Apr 2026, online)
- Add potential solutions agreed in merged CR
- Progress on/finalize conclusions and recommendations including potential normative work and further study
- Finalize related Stage 2 draft WID
- Initiate early draft of TS 26.nnn
- Communicate with other 3GPP WGs and external organizations

### SA4#136 (May 2026, Montreal, CA)
- Add conclusions and recommendations including potential normative work and further study in merged CR
- Finalize recommendations and conclusions
- Agree on merged CRs to TR 26.942
- Agree Stage 2 WID
- Progress on early drafts of TS 26.nnn
- Communicate with other 3GPP WGs and external organizations

### SA#112 (June 2026, Singapore, SG)
- Approve merged CRs to TR 26.942

## Proposal

The document proposes the above Work Plan for SA4 team consideration.